Solar Shed -- Shed and Collector Wall

Shed and Collectors

 

The storage shed is 24 ft by 12 ft, with the long dimension facing south.  The shed is adapted from one described in "Build a Shed", Taunton Books.  It has a gambrel style roof, which has been modified on the south face to allow a maximum area to integrate solar collectors (see picture).  The south wall of the shed uses conventional 2X6 24 inch on center framing with OSB sheathing.  The collector frame is mounted directly to this sheathing (the sheathing is the back wall of the collector).   The collector glazing also acts as most of the south wall siding and roof.  This sharing of components reduces material use and cost for both the shed and the collector.  

 

The collectors are site constructed, but use an absorber plates that were purchased pre-assembled. 

 

Since this is a drain back system, the absorber plates must be installed such that they have a drainage slope toward the storage tank -- this insures that the water in the collectors drains when the pump is turned off.

 

 

The shed design was adapted from the one pictured here, which is from a Taunton "Build A Shed" book.  Basically, the steep part of the roof slope on the south side was extended all the way to the ground so that it forms both the roof and the south wall.  This makes an about 11 ft high surface for integrating solar collectors.  The length of the shed was increased from 16 ft to 24 ft to provide more storage area, and more collector area.

 

 

There are six collectors of 4 ft by 10 ft each.  The collectors are integrated with the south wall of the shed.  The collectors are site built, but use pre-assembled commercial absorber plates.

 

 

 

Click images for full sized pictures

 

 

 

 

 

 

 

 

 

 

 

 

The finished Solar Shed with 240 sqft of solar water heating collectors in south wall

 

 

 

 

 

 

 

 

Collectors -- Make or Buy?

There are several options on how to make/buy the collectors:

I chose the third option of ordering pre-made absorber plates, and making the framing myself.  This offered a substantial cost saving from commercial collectors, and a substantial labor saving from making the full collector myself.  It also allowed me to better integrate the collectors with the wall and make maximum use of the wall space for collectors.   The resulting collectors cost about 1/4 what commercial collectors cost -- a $5500 saving.

 

This paragraph updated October 31, 2011: I ordered my absorber plates from SolarEnergy, a company that has since gone out of business.  Some of the makers of solar collectors will sell absorber plates SunEarth would be one place to try -- the prices don't appear to be as good as when I got my plates.   Another possible source that several people have used is  http://www.sunraysolar.com/index.php .    Other possibilities here -- sources .  If I were doing this project today, I would make the collector absorber plates as is done in this project...

 

 

Cost of Collectors Per Square Foot

 

Item Cost ($/sqft) Notes
Absorber Plate 6.20 from solarenergy.com
Twin Wall Polycarbonate glazing (1) 1.50  
Other Glazing components 0.40 glazing retaining strips
Insulation (1 inch) 0.50 one inch polyiso insulation
Collector Frame 0.25 2X4 framing
Siding credit -2.00 collector glazing provides siding
Total $6.85 about 1/4 of commercial collectors

(1) If using polycarbonate glazing, see the section on collector venting below.


The table does not include shipping charges, which can add up if you can't get glazing and absorber plates locally.

 

Shed Construction

The pictures below show a bit of the construction of the shed.

Since most people will want a different style shed, I have not included much detail on the shed construction.

The main idea is to provide a large south wall that is well oriented for solar collection, and to integrate the collectors with the wall as much as possible.

 

Click images for full sized pictures

The basic framing of the shed.   It is supported on concrete piers, and uses mostly ordinary stick framing.  The gambrel roof area is constructed with homemade trusses that leave a large, open storage attic.

The excavated area just that is just visible inside and to the right is where the thermal storage tank lives.

 

 

 

 

 

 

 

 

Building the roof trusses for the shed in the shop.  The stacks of precut lumber in the back are for the rest of the trusses.  With some marks on the floor, and everything precut, the truss building goes surprisingly fast.  Each truss is light enough for one or two people to put in place easily.

 

 

 

 

 

 

 

One thing to be careful of is that the stud spacing must line up with the collector frame (described below).  Since most of the twinwall glazing panels want their supports spaced 48 1/4 inch apart, the stud spacing will probably want to be a bit over 24 inches to so that the centerline to center line distance over two stud bays is 48 1/4 inch, not 48 inches. 

 

Collector Construction

The next four pictures show how the collector frame can be laid out  on a flat surface to save some time and increase the chances of things fitting. 

The collector frame 1) holds the absorber plates in position, and 2) supports the glazing panels. 

To preview how this frame fits on the shed collector wall, skip down a few pictures.

 

Cutting and prparing the collector framing:

This shows laying out the collector frame on the driveway to make sure everything fits.

Use a chalk line to layout the collector dimensions on the driveway (or any flat surface).

Once you have checked that the dimensions are correct, precut all the pieces of the frame.

Once you have the frame laid out, its a good idea to trial fit an absorber panel, and a glazing panels.

(note the glazed shop doors in the background -- these glazed doors heat and light the shop all winter -- the white filler panels are installed in the summer to reflect some sun and prevent overheating.  A standard overhead garage door behind the glazed door provides night insulation ... more)

 

 

 

 

 

Marking off the line for notches that the top collector manifold is going to be supported by.  For drain back systems, this must be sloped at least 1/8 inch per foot toward the supply line end of the manifold -- more is better.

 

Marking all of them at once in this saves time, and reduces the chance of errors.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

All of the vertical frame members cab be clamped together to so that the notches for the glazing supports can all be cut at the same time.  This also insures that all the glazing support notches will line up.

 

The notches visible at the bottom support the collector absorber plate lower manifold.  Note the down slope for drainage.

 

Note! -- no manifold notches in the end (most east and most west) frames.

 

 

The things to accomplish at this stage:

- Notches to support upper and lower manifolds.

- Notches for the EMT glazing supports.

- Holes for the lag screws that hold these framing members to the collector wall studs.  Drill a shallow large hole to counter sink the lag screw head into, and then a pilot hole all the way through.

 

 

 

 

 

This is also the easiest time to do the painting.

 

 

 

 

 

 

 

 

 

 

Installing the collector bay framing:

 

 

This shows the collector wall with the OSB sheathing installed and painted.

The first (center) 2X4 for the collector frame is being positioned.  Do this one VERY carefully. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

In mounting this first vertical, make sure the following conditions are satisfied:

The vertical 2X4's at the edge of each collector must be correct if the glazing panels are to fit, and this first, center frame is the one that sets up all the rest.  So, make sure its right.

 

Attach the center vertical frame to the underlying wall stud with 6 inch lag screws, using the holes that you pre-drilled earlier.  Make sure the heads of the lag screws do not stick out above the face of the 2X4 that the glazing is going to be mounted to.

 

The open horizontal slots in the OSB are for a venting system to prevent collector overheating when the collector is stagnated -- see Collector Venting below.

 

This shows the collector frames being built on the OSB sheathing.  Each 4 ft collector bay has a vertical 2X4 on each side, and horizontal 2X4's at the top and bottom. 

 

Once the center 2X4 in in, the 2X4's at the top and bottom of the adjacent bays can be installed -- these will precisely set the spacing to the next vertical 2X4.  For the 48 inch wide twinwall glazing that I used, the center to center spacing of the verticals is 48 and 1/4 inch -- the panels are 48 inches wide, and the 1/4 space allows for some expansion.

To insure that the vertical 2X4's do not wander off plumb, use a scrap spacer 2X4 that is cut to the bay width to check the spacing at several points -- that's what the unpainted 2X4 in the picture above is being used for.  All this precision is to make sure the glazing panels fit properly.

 

 

Its a good idea to have one of the glazing panels handy to check that the spacing of each bay is correct as you go.

 

Installing Insulation Panels:

 

 

 

 

 

This shows the polyisocyanurate insulation board being installed in the collector bays.  This insulation reduces heat loss out the back of the collectors.

The panels are one inch thick, and cut nicely with a razor blade knife.

Be sure to use the polyisocyanurate  insulation, as the polystyrene (pink, blue and white stuff) will NOT hold up to the temperatures (trust me on this).

Most lumber yards carry the polyiso, but may not know it by that name.  It is usually light brown in color, and has face sheets of alum foil or fiberglass.

 

 

 

 

 

 

 

 

 

 

Installing the collector absorber plates:

 

The absorber sheets positioned for soldering by temporary scrap wood supports.  They are supported about 4 inches out from the collector frame by the temporary supports.  Once all the panels were soldered together, they were just slid back as a unit into the notches on in the 2X4 collector frame. 

This was a method I used to avoid putting unions in between each absorber plate.  I think that if I were doing it again, I would probably use the unions.  The negative side of the unions is they are a bit spendy, and I have seen many reports of leaks at unions.  The plus side is that they allow easier assembly, and allow easier replacement of an absorber at some (hopefully) very distant time.

 

 

 

 

 

 

These are the scrap wood jigs I used to position the panels for soldering.

The notch in the small one (upper left) just fit over the upper manifold, and held it out about 5 inches.

The left one supported the lower manifold about 4 inches out.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

This shows soldering one of the manifold connections using an ordinary 1 inch copper pipe coupling.

Once they are all soldered, the whole 6 panel assembly is pushed back into the supporting notches in the 2X4 collector frame.

 

 

See the "Lessons" section for a potentially better way to do this.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Shows the absorbers in their final position.  Note the 4 inch down slope from the west side to the east side for drainage.  The horizontal metal members that are 1/3 and 2/3rds of the way up the collector are supports for the glazing to eliminate buckling of the twinwall glazing as it warms up.  They are made from EMT electrical conduit, with a bead of silicone caulk between the twinwall and the EMT. 

Update: I would recommend positioning the upper EMT glazing panel support closer to the top -- the panel tends to deflect more at the top, so this is where the support is best positioned.

 

 

 

 

 

 

 

 

 

 

 

Picture of the EMT conduit glazing supports.  I used a bead of silicone caulk to keep the glazing from directly contacting the galvanized surface of the EMT.

These EMT "supports" do not really do any supporting of the glazing, they just keep the glazing panels from buckling as they warm up.  EMT is cheap, straight, and galvanized, so it should last well.

 

 

 

 

 

Glazing:

Showing four of the 6 twinwall polycarbonate glazing panels installed, with two to go.  The glazing panels are secured in place with 1X2 members and stainless steel screws.  There is no caulk, glazing tape, or gasket between the polycarbonate and the 2X4 edges of the collector frames. 

 

The panels are simply pushed against the 2X4's with the 1X2's battens.  So far, this seems to be working fine, and keeps the water out.   This arrangement (it is claimed) allows the PC panels to expand more easily -- I'm not so sure about this, but one advantage it does definitely have is that its very easy to remove the glazing panels if (for example), you missed a solder joint inside the collector :)

 

 

 

 

 

For the vertical 1X2 ish battens that hold the glazing in place, I tried one of the plastic deck woods.  Ordinary wood can be used for this, but a number of sources have said that it does not hold up well with the constant exposure.  My logic is that the plastic deck woods are supposed to last more or less forever in deck applications, and so may have a good life for this application.  There are also a number of commercial choices of twinwall panel edge hold downs -- your glazing supplier will no doubt have some.

 

A drain hole is provided at the bottom of each collector bay to drain any water that happens to get in.   Except for the leak caused by my bad solder joint, I have not seen any water get in, and we have had a couple good rains.

 

Note that after this picture was taken I extended the roof edge about 5 inches to prevent any tendency for wind driven rain water to get into the collector boxes.  I plan to add a gutter so the collectors don't get runoff from the roof.  Update: the gutter should definitely be included, in that when snow accumulates on the roof, and then melts, it tends to drop onto the glazing panels bringing some dirt with it.  The other option would be to make the collectors vertical, which I have come to think is a better all-around arrangement.

 

Finished collector

 

Collector Venting

I was a bit concerned about the glazing becoming overheated when the collector is stagnated (no fluid being pumped through it).  I decided to include air vents in the back wall of the collector that would allow cool air from inside the shed to enter the collector near be bottom through a lower vent, and heated air to exit the collector near the top.  This effectively makes a thermosyphon air collector, and should keep the stagnation temperatures down.  This paper discusses a somewhat similar approach: http://www.builditsolar.com/Experimental/44-31-%20Harrison1Stagnation-temp-control.pdf.  I am working on some type of thermally actuated gadget to close the open the vents automatically when the temperature exceeds (say) 190F.

 

These vents should be screened to keep the critters out.  There should be a small airflow passage on the back side of the absorber plate, so that any dust in the air does not settle on the sun side of the fins.

 

It appears that these vents (or some equivalent form of cooling) are required for the stagnation condition.

 

 

This chart shows the temperature of the inside surface of the glazing near the top of the collector.

This is around solar noon.  Initially all the collector vents are closed.

At minute 1, the circulation pump is turned off, and the collector temperature starts to rise.  It continued to rise until it leveled off at about 205F around minute 8.  At this time, the temperature of back near the absorber surface is a bit over 300F. 

I opened the vents at minute 9, and the glazing and collector temperature immediately begin to drop, and eventually reach a very nice 110F.

This was done under sunny conditions, Tambient about 60F, and windy.

 

In a later test the next day, with Tambient at about 25F, the collector reached even higher temperatures, and the glazing near the top of the collector had a noticeable inward deflection from the expansion.  This did not look good to me for the long term health of the polycarbonate panels.  The polycarbonate glazing is listed as having a temperature capability of 270F, and I don't believe that this was exceeded, but I don't think it would be good to routinely expose the panels to these relatively high temperatures.

 

While I plan to do some more testing, my tentative conclusion is that this collector when glazed with twinwall polycarbonate needs some form of cooling when stagnated under sunny conditions.

One thing to be alert to is that this high internal temperature condition develops very quickly when stagnation occurs under sunny conditions.

 

The following are possibilities to resolve this overheating issue:

Some other things that I plan to do on my collectors that I think will improve the situation (but probably not eliminate the need for ventilation at stagnation):

I believe that the combination of making the collectors vertical and somewhat deeper (use 2X6 framing) will eliminate any serious tendency for overheating.  Its still not a bad idea from a glazing life point of view to keep the collectors from cooking all summer -- this might include: 1) seasonally used vents as described above,  2) an overhang that shades part of the collector from the high summer, or 3) a shade cloth covering.

 

I am still looking for a good way to automatically open a cover on the upper vent when the temperature in the collector exceeds (say) 200F, and close when it goes below this.  Any ideas?

 

Update: 1/15/07

Vertical Collectors:

My thinking in using collectors tilted at 70 degrees was that this is a good angle for winter collection, and that it looked better with the shed (basically its just an extension of the gambrel roof slope to the ground).  While the 70 degree tilt is not a bad scheme, I have come to think that a vertical collector would be an all-around better choice for these reasons:

All of this said, if you have a reason that you prefer tilted collector, it will work just fine.

 

Collector Construction:

A few things I might do differently on the construction:

 

 

Gary Updated 10/25/06

Updated 10/31/06, 1/15/07