Charging the Elec-Trak Using a Grid-Tied PV Array

One of the major aims for the Elec-Trak project is to be able to use the Elec-Trak battery pack for power during power outages AND to be able to recharge the Elec-Trak pack from our grid-tied PV array.

This section covers our somewhat brute force method for charging the Elec-Trak from the PV array.

Solar Elec-Trak

Back to the Elec-Trak Table of Contents...

Overview

We have a 2.15 KW grid-tied PV array that helps offset some of our power use.  Our PV array is grid-tied and uses the Enphase micro-inverter system with one micro-inverter on each PV panel.   Since this is a grid-tied PV system without battery backup, when the utility power goes down, our PV array goes down a well -- even if the sun is shining, we get no power.  Grid-tie inverters are required to shut down when they sense that grid power is no longer there -- this is a safety feature meant to protect utility workers working on the line. 

It is possible to do grid-tied systems with battery backup.  In the case of a power outage, these systems disconnect from the grid and supply limited power to the house from their batteries via the inverter.  We elected not to do this because the systems are considerably more expensive, and because of the high cost of replacing batteries over time.  The added costs of buying and replacing batteries can all but wipe out the savings from reduced power usage, and this just did not seem worth it given that our power is pretty reliable. 

So, now with the Elec-Trak we have a large set of batteries that is earning its keep on mowing and snow blowing tasks, we ask ourselves if there is not some way to 1) use these batteries to power the house in emergencies, and 2) charge the batteries with our existing PV array?

The first item of powering a few critical house loads during an emergency from the Elec-Track batteries is a pretty easy yes, and is covered here...

The 2nd item  is more challenging.  The solution we came up with for using our current PV array to charge the Elec-Trak during a power outage is a bit brute force, but is pretty simple and pretty easy to implement for our type of system.  In a nutshell, we bought an off-grid style charge controller, and then rewired six of the PV panels to suit the charge controller.  The charge controller then charges the Elec-Track battery pack.  For the duration of the power outage, we effectively convert a portion of our grid-tie array into a typical off- grid array -- details below.

This sounds like a somewhat extreme approach, but it actually is surprisingly straight forward to do, and is relatively inexpensive.  The only significant expense is the charge controller, which was $450.  While rewiring the PV modules seems like an involved thing to do, its actually straight forward, and the time to go from grid-tie configuration to off-grid configuration is under half an hour.    What this gives us is a reliable, long term, quiet, emergency power source, AND it does not require us to maintain and replace a separate set of batteries that would be just sitting there doing nothing 99.9% of the time -- we just use our Elec-Trak batteries that are already earning their keep.

The Hookup
 

 

Safety Warning and Disclaimer

 

There are serious safety issues involved with wiring PV systems.  The voltages  can be high, and potentially lethal.  When you couple electric shocks with working on the roof, there is an obvious potential for serious accidents. 

 

PV systems have the added hazard that even when the grid power is turned off, the system can be "live" and present a serious shock hazard -- hundreds of volts on some systems.

 

I want to make it very clear that I am not an electrician, and I take no responsibility whatever for the correctness of the wiring hints below -- you need to do your own homework!

http://www.builditsolar.com/Contact/legal.htm

 

Charge Controller Input from PV Modules

The heart of the system that charges the Elec-Trak from our PV array is the Xantrex MPPT60-150 charge controller.  This charge controller will accept a wide range of PV panels as input and will charge a battery packs that are 12, 24, 36, 48, or 60 volts.   It is one of a few charge controllers that will charge a 36 volt battery pack like the one in the Elec-Trak.   It is also an MPPT (Maximum Power Point Tracking) charge controller, meaning that it adjusts the PV module input voltage to the point where the PV panels will produce the most power for the current sun conditions.  

 Similar flexible charge controllers are made by Outback, Morning Star, and probably others.

The charge controller requires that its input voltage from the PV panels fall within a range of voltages that the charge controller is designed to accept. You must configure your PV modules into series strings that fall within the allowed voltage -- typically, these are strings of 2 to 5 modules depending on the characteristics of the modules.    Xantrex (Schneider) provides a tool that will allow you to pic the type of module you have and the voltage of your battery pack, and the tool will give you the number of modules that need to be connected in each string, and how many strings are allowed.  In our case (REC 215 PV modules) it is possible to use strings of either 2 or 3 modules, and anywhere from 1 string to 6 strings can be accommodated. 

We decided on 2 strings of 3 PV modules each.  This uses 6 of our 10 PV panels and gives up up to 1290 watts with full sun.   If there is a need in the future, we could easily go to 3 strings modules for 1935 watts.

Mounting and Wiring the Charge Controller

 

Rewiring the PV Panels

So, normally on our PV array, the two leads from each PV panel are plugged directly into the micro-inverter for that panel.   

For the new emergency power setup, the first 3 PV panels must be wired into one series string, and this string hooked up to the charge controller, and likewise panels 4 through 6 are wired into a 2nd series string and also hooked up to the charge controller. 

All of the PV panel connections are made with the standard MC4 connectors.  So, the "rewiring" is just a matter of unplugging MC4 connectors from one place and plugging them into another place.   The MC4 connectors snap into place, and it is helpful to have the little tool that releases the snaps when undoing the connections.  The wiring sketch below shows the connections as we made them.

Note that a new cable is needed to make the connection from the negative lead of the first PV panel to the charge controller, and a 2nd new cable to make the connection from the positive lead of the last panel in the string to the charge controller.   This is most easily handled by buying an MC4 extension cable, and cutting it in half -- each half gives you one of the new cables. 

Charge Controller Output to Battery Pack

The Xantrex charge controller we are using accepts battery packs of 12, 24, 36, 48, or 60 volts.  When the system is started up, the Xantrex normally detects the battery pack voltage and adjusts accordingly, but if not, you just set it to the nominal voltage of your battery pack. 

The charge controller output cable simply plugs into the same outlet on the Elec-Trak that the old external charger plugged into. 

Mounting and Wiring

The charge controller must be protected from rain, so it is mounted in a simple, portable plywood enclosure.  The enclosure is just large enough to meet the required clearances around the charge controller for ventilation.  A fused disconnect switch is mounted below the charge controller.  The switch disconnects the PV modules from the charge controller and also provides overcurrent protection.   The fuses and switch need to be DC rated  to the appropriate values. 

ChargeController  


The Xantrex charge controller mounted in its little shelter
out on the PV array.  It hangs on one of the PV array supports.
During times between power outages, it lives in the barn.

 

The charge controller, disconnect, and its plywood shelter are normally stored out of the weather inside the shop.  When there is a power outage, we take it out to the PV array and hang it on one of the PV array support posts.  The wire connections to the PV array and battery are permanently connected to the charge controller and just coiled up and stored with it. 

     
     
     

 

 

The actual sequence in which the connections are made and switches flipped etc. are covered in the Test section just below.   It is important from both a safety and protection of equipment point of view to do the change over from grid-tie to emergency power and back in the right sequence. 

The Test

Since we don't get power outages very often, I went ahead and did a simulated power outage so that we could make sure the system actually worked and get the sequence down.  So, here is the whole sequence.

 

Start up:

1- Mounted the charge controller on the PV array support post so it is ready to be hooked up.  Pulled the Elec-Trak up close to the charge controller.

Checked that the DC disconnect switch below the charge controller was in the open position.

2- Covered the PV panels that will be rewired with a tarp to shade them.  This is so that when panels are disconnected and reconnected, no current is flowing. 

3-  Switched the AC disconnect for the PV array to the off position.  This disconnected the PV array from the utility grid.  The AC disconnect needs to remain in the OFF during the whole time you are operating in the emergency power configuration.

When we threw the AC disconnect for this test, it was the first time in the two year life of the system that it had been used!

4 -Hooked up the ground connection from the charge controller to the PV array rail.

4- Did the reconnection of the PV modules into the two strings of three modules each:

- Disconnected the negative lead of the first PV module from the micro inverter and just left it hanging for now.

- Disconnected the positive lead on the first PV module and the negative lead on the 2nd PV module from their micro-inverters, and connected them to each other. 
Repeated this for the 2nd panel positive to 3rd panel negative leads.

- Disconnected the positive lead on the 3rd panel from its micro-inverter.  Checked the voltage of the first string with a volt meter.  There was enough light leaking through the tarp to verify that the polarity of the string was correct and the voltage was reasonable.
Connected the negative lead from the first panel to the charge controller negative cable for string 1.
Connected the positive lead from the 3rd panel to the charge controller positive cable for string 1.
This completed the rewiring for the first string.

- Repeated the steps above for the 2nd string.

5 - Opended the battery circuit breaker on Elec-Trak. 
Hooked up the battery pack to the charge controller by plugging in the in the big grey 3 prong plug.  This is where the old external charger plugs into the Elec-Trak pack.  For this test, there was an open in this circuit somewhere, and rather than spend time finding it, I made temporary connections with the yellow and green wires in the picture to hook the charge controller to the battery pack.

6- Uncovered the PV panels.
Closed the battery circuit breaker in the Elec-Track (this hooks the charge controller to the battery pack, and the charge controller starts to come up).
Closed the PV disconnect (this connects the PV modules to the charge controller).

7 - Went through the little Q and A with the charge controller on its LCD panel.  Just answered a couple questions about battery type, etc. 

8 - As soon as the dialog was completed with the charge controller, it started charging the battery pack at about 280 watts.   The wattage was low because it was cloudy.

9 - Simulated house loads on the Elec-Trak charger/inverter by hooking up a 1200 watt space heater to the inverter 120VAC outlet.
Ran this for about half an hour.  Nothing unusual -- the charge controller continued to charge.

-----------

Shut Down:

10 - Covered the PV modules with tarp.

11- Open the PV disconnect. 
Charge controller shows "Charger off -- low light" message.

12- Open the battery circuit breaker.
Charge controller turns off (goes dead).

13 - Redid all the MC4 PV module connections to their original connections with the micro-inverters.

14 - Uncover PV panels.

15 - Once all the wiring was back to normal, closed the AC disconnect at the house.
The Enphase micro-inverters came back up to normal after a few minutes -- PV system operating in normal grid-tied mode after a few minutes.

This seems a bit involved, but took less than half an hour for the first time hookup into the emergency mode. 

 

 

 

 

 

 

 

Gary
December 13, 2011